Play the data center

What is really happening

Insatiable demand for data — can you build a data center in America?

The buildings are rarely the slow part. Power, transformers and the county are — and in September each of them moved.
The game's world at golden hour: a data-center campus going up in the desert, a crane lifting a roof fan, crews in hard hats, and a heavy-haul truck bringing a power transformer to the gate.

A data center for artificial intelligence needs as much electricity as a small city, and it needs it on a date. The halls can be raised in months. The line to the grid, the transformers that step its power down and the county's permission take years, and none of them can be bought faster with money alone.

That is the trap the game is built on. A careful player finishes the halls early and then waits — on the utility's queue, on a transformer still at sea, on a vote that went the other way — while the tenant's deadline comes closer every month.

The calls below are this month's, made by real officials and companies, with the reasons they gave. Each one is a door the game opens in a run.

The real calls

Who decided what, and why

Sep 21, 2026

Gov. Greg Abbott (Texas)

Ordered the state environmental agency to halt all data-center permits

On September 21, Gov. Greg Abbott ordered Texas’s environmental agency to halt all data-center permits until audits of the grid and water are done.

Sep 22, 2026

Pima County Board of Supervisors (Arizona)

Voted 3–2 for a 120-day pause on new data-center projects

On September 22, Pima County, Arizona, voted 3–2 for a 120-day pause on new data-center projects.

Sep 24, 2026

Oracle

Sent a force-majeure notice on a Stargate campus in New Mexico

Oracle sent a force-majeure notice on a Stargate campus in New Mexico, which lets it delay payments if the site misses its 2028 target. The gas pipeline meant to supply it has slipped to February 2027.

Sep 17, 2026

Nevada regulators

Approved two temporary gas plants, 362 megawatts in all

On September 17, Nevada regulators approved two temporary gas plants, 362 megawatts in all, to power data centers where the utility can’t keep up.

July 2026

Virginia regulators

Ordered Dominion to make large users pay directly for some new transmission lines

Virginia regulators ordered Dominion in July to make large users pay directly for some new transmission lines. Microsoft has appealed.

Aug 31, 2026

Arizona Attorney General Kris Mayes

Called for a statewide pause on new data centers

Arizona’s attorney general called for a statewide pause on new data centers, pointing to water and power bills.

The reason given: Water and power bills